LARMAC continues the pool renovation project with Boreal Plunge, Celestial Plunge, Cherry Plunge and the Flintridge Clubhouse Pool & Spa.
LARMAC continues the pool renovation project with the commencement of four pools starting on Monday, January 18, 2021. This final phase of the pool renovation project includes Boreal Plunge, Celestial Plunge, Cherry Plunge and the Flintridge pool & spa.
According to LARMAC project lead, Dan Papanic, this scheduled scope of work is being completed because the pool plaster is past its ‘useful life’ and is showing signs of deterioration.
The estimated date for the pools to reopen is Saturday, May 1, 2021 which is subject to change.
Residents may see the status of LARMAC-managed pools at LaderaLife.com/PoolStatus
Schedule:
BOREAL PLUNGE
Closed on Monday, 1/18/2021 to
drain the pool.
Demo of existing plaster is scheduled
for 1/19 to 1/20.
CELESTIAL PLUNGE
Closed on Tuesday, 1/19/2021 to
drain the pool.
Demo of existing plaster is scheduled
for 1/20 to 1/21.
CHERRY PLUNGE
Closed on Wednesday, 1/20/2021 to drain the pool.
Demo of existing plaster is scheduled for 1/21 to 1/22.
FLINTRIDGE CLUBHOUSE POOL & SPA
Closes on Sunday, 1/24/2021 to drain the pool and spa.
Demo of existing plaster is scheduled to start on 1/26.